9-101 Wash Bay Relocation

Completed construction for the decommissioning, demolition, removal, and reinstallation of an existing active wash bay, frame assembly, and supporting utilities within a 7-week time period. Scope included prepping the new site for installation of a wash bay assembly, and installation of new footings, columns, and utilities on the front end.  The bay itself was then decommissioned and moved throughout an active facility, reassembled, reconnected, and recommissioned within the time allotted.